NEWS AT BUKANGA-LONZO

INFOS DE BUKANGA-LONZO

Breaking News

Nouvelles Chaudes

  • TRIOMF RDC FERTILIZER PRODUCTION TESTS

    cover image test

     

    Discover the plant on the harbour port of Boma in the Democratic Republic of Congo. Since 2014, this production facility is part of a limited company with a public-private partnership. Explore the factory by viewing the video below.

    Read more...
  • SILO CONSTRUCTION PROGRESS

    00010 cover silo

     

    We are installing the final silo bridges. These bridges connect the grain tower with each other. A inclined conveyor method is used to fill these towers with the harvested grain.

  • MARKETING AT MINI MARCHÉ – MASSINA

    marketing at the massina shop

     

    The chain of Mini Marché shops have started a marketing campaign promoting the new look of the shops. There also might be a competition in the near future – STAY TUNED!

  • MAIZE STORED IN THE SILO COMPLEX FOR THE FIRST TIME

    00011 cover image

     

    The first maize is stored in a wet holding bin after which they will be transferred to a dryer at a later stage. The fact that we are able to store the maize directly on the farm is a great achievement. For more, please visit the Silo Complex gallery.

    Read more...

TRIOMF RDC FERTILIZER PRODUCTION TESTS

cover image test

 

Discover the plant on the harbour port of Boma in the Democratic Republic of Congo. Since 2014, this production facility is part of a limited company with a public-private partnership. Explore the factory by viewing the video below.

Read more...

SILO CONSTRUCTION PROGRESS

00010 cover silo

 

We are installing the final silo bridges. These bridges connect the grain tower with each other. A inclined conveyor method is used to fill these towers with the harvested grain.

MAIZE STORED IN THE SILO COMPLEX FOR THE FIRST TIME

00011 cover image

 

The first maize is stored in a wet holding bin after which they will be transferred to a dryer at a later stage. The fact that we are able to store the maize directly on the farm is a great achievement. For more, please visit the Silo Complex gallery.

Read more...

MINI MARCHE SHOP LOOKING GOOD

00001 mini marche cover

 

All of the Mini Marche shops in and around Kinshasa have been given a facelift. The new branding is up and looking good.

Read more...

MAIZE SEASON 2016

00001

 

The first hectares that were planted are ready for harvesting and not only are we excited about the yield but we have the privilege of storing the first harvested maize in our state-of-the-art silo complex. For more, please visit the Silo Complex gallery.

Read more...

NEWS AT BUKANGA-LONZO

video cover

 

Please click on the read more button to view the full video.

Read more...

MAIZE SEASON 2016

cover bullet 1

 

The first maize cobs are looking extreamly good. As you can see in the image the cobs are full of golden kernels and will soon be ready for harvesting For more photos of the progress please visit our gallery.

Read more...

MAIZE SEASON 2016

cover bullet 1

 

The first hectare maize crops are nearing the drying stages. That will soon be ready for harvesting. For more photos of the progress please visit our gallery.

Read more...

MAIZE SEASON 2016

cover bullet 1

 

The first maize cobs are starting to form. Everything looks great and the maize growth is on point. For more photos of the progress please visit our gallery.

Read more...

MAIZE SEASON 2016

cover bullet 1

 

Here is an update on the growth progress for the first hectare maize that was planted. As you can see on the image the maize has grown to about shoulder level. The colour is also a healthy green and we are all very gratefull that the season has been blessed so far. For more photos of the progress please visit our gallery.

Read more...

GROWTH PROGRESS OF PEANUTS ON THE PARC

peanuts cover

 

Growth progress of the first hectares peanuts planted on S.E. du Parc Agro

Read more...

MAIZE SEASON 2016

maize 2 cover image

 

We are very blessed with the progress so far on the first hectares we planted mid-October 2016. Please visit our Gallery for more images of the start and progress of this season's maize.

Read more...

MAIZE SEASON 2016

Maize Season 2016 16 cover

 

Growth progress of the maize planted in mid-October. Here you can see the crops are starting to produce maize cobs.

Read more...

MAIZE SEASON 2016

Maize Season 2016 5 cover

 

After careful planning and preparation, we planted the first hectares for the 2016/2017 maize season in mid-October. We will soon start with the preparations to plant to remaining hectares. For more photos please visits our gallery.

Read more...

BRIDGE PROJECT

Parc Agro Bridge Project 11 Cover

 

We have finished with the second phase of steel preparation. The second phase of concrete has started.

Read more...

CONSTRUCTION OF POWERLINES

Parc Agro Constuction of power line 1 Cover

 

The concrete base footing of the first five power lines is complete.

Read more...

BRIDGE PROJECT

Parc Agro Bridge Project 1 Cover

 

The bridge is currently in elevation and is set in place. Everything is in order to start with the cross bracing.

Read more...

HOUSING STRUCTURES

Parc Agro Housing Structures 2 Cover

 

Final ground works around the second house is almost finished.

Read more...

SILO CONSTRUCTION PROGRESS

Silo Complex 30 Cover

 

Silo complex nearly complete. We only have to install the top dryer, then we are finished.

HOUSING STRUCTURES

housing structure 1 cover

 

Construction on the second apron house is nearly complete. We are currently doing the necessary preparations to insert the ceiling boards.

Read more...

SILO CONSTRUCTION PROGRESS

Workers celebrating final silo ring.wmv snapshot 00.17 2016.10.13 10

 

Workers celebrating the installation of the final silo ring of the last big silo. For the full video visit our gallery under videos.

SILO CONSTRUCTION PROGRESS

Parc Agro Silo constuction 24 Cover

 

Second bucket elevator installed and ready for operation.

SILO CONSTRUCTION PROGRESS

Parc Agro Silo constuction 20 Cover

 

Progress on the silo complex, our first bucket elevator is installed.

SILO CONSTRUCTION PROGRESS

Parc Agro Silo Construction 16 Cover

 

Apron preparation and finish around the silos’ wet-and-dry bins.

SILO CONSTRUCTION PROGRESS

Silo Constructio 13 Cover

 

We have installed the wet bin gantry on the silo complex.

BRIDGE PROJECT

parc agro bridge project cover

 

The bridge project is still underway. For the newest update please visit our gallery.

Read more...

SILO CONSTRUCTION PROGRESS

silo cover constr pro

 

The silo complex construction is moving along with great progress. Please visit our gallery for the latest photos.

A VERY SPECIAL VISIT TOOK PLACE AT S.E. DU PARC AGRO

special visit cover

 

On 18 September 2016, we were privileged enough to host the Prime Minister Matata Mpony and a delegation of Ministers visit S.E. du Parc Agro. Amongst these delegates where the new Governor of the Kwango Province, Kabula Larousse and Vice-Governor Kaputu Vita Emery.

Read more...

S.E. PARC AGRO VISIT SEPTEMBER 2016

s.e. parc agro visits cover

 

A group of approximately 30 guests visited the Parc in the past week. Amongst these guests were Senior Advisors and their teams from the Prime Minister’s office, as well as 3 guests from IL Quadrato s.r.l. We took these guests on a tour to show them exactly what we have done at the Parc and also to show them the progress on current projects, such as the silo complex, feed mill, cassava processing factory, pivot dams and pivots to name but a few. For more on this visit our gallery.

Read more...

AERIAL VIEW

Silo Complex Feed Mill area and Cassava Processing Factory

 

An aerial shot of the Silo Complex, Feed mill area and Cassava processing factory. For more on these projects visit our gallery.

AERIAL VIEW

Aircraft Hanger Airstrip Workshop and Warehouses

 

Here you are able to see the Aircraft hangar, Airstrip, Workshops and Warehouses. For more on these project visit our gallery.

AERIAL VIEW OF THE GREENHOUSES COMPLEX

arial view greenhouse complex

 

An aerial shot of what the finished greenhouses complex looks like. For more on this project visit our gallery.

AERIAL VIEW OF THE INFRASTRUCTURE

Infrastructure View

 

We are so proud of what the Parc has accomplished up to date. Here is an aerial view of the infrastructure on S.E. Parc Agro.

SILO CONSTRUCTION PROGRESS

Cover Silo Complex20

 

Another image of what the silo complex looks like up to date. Please visit our gallery for more image on the progress.

BRIDGE PROJECT

Cover Bridge Project 3

 

We have filled up the road that leads to the temporary river structure. Now we will have better and safer access to this area so that we can continue with the construction of the permanent bridge.

Read more...

SILO CONSTRUCTION PROGRESS

Cover Silo Complex 3

 

Here is an image of what the wet bins look like inside. For more images on the progress of the silo complex visit our gallery.

RUNWAY CONSTRUCTION

runaway construction cover

 

Taxiway drainage system preparation for the runway.

BRIDGE PROJECT

bridge project cover1

 

We started to dig the foundation for the bridge. The first foundation shutter is also in place.

Read more...

PREPARING PIVOT LANDS FOR COVER CROPS

Lime10 cover

 

We are currently spreading lime on the pivot lands for the cover crops using a BPI Twister.

WEIGHBRIDGE CONSTRUCTION PROGRESS

weighbridge construction cover4

 

We have entered the final stages of construction for the weighbridge. A few final trimmings remain, after which we can start with the calibration process.

BRIDGE PROJECT

bridge project 2 cover

 

The bridge structure has been built on Site A and will be loaded for transport to the bridge site 30km away.

Read more...

BRIDGE PROJECT

bridge project 3 cover

 

Half of the bridge structure has arrived at the bridge site.

Read more...

HOUSING STRUCTURES

housing structure 6 cover

 

House 2’s roof is almost finished and the walls are being painted.

Read more...

MILL CONSTRUCTION

mill construction progress27 cover

 

The shuttering and preparation on Pit E has been completed, the floor is ready for steel reinforcing and starter bars for the shutter walls.

SILO CONSTRUCTION PROGRESS

silo construction 6 cover

 

The last ring on the silo has been installed and stands at an impressive height of 30m and a width of 20m.

THE CASSAVA PROJECT

cassava project1 cover

 

We have employed local women to help us with the current cassava project at the Parc. The women help by peeling the roots of cassava plants to be used in the process of making cassava meal. After the cassava roots are peeled they are washed and placed inside a special machine that finely grate the roots into cassava flakes. The cassava flakes are then placed in soaking dams for a few days to soak out the starch. When this process is finished the cassava flakes are drained from these dams where they are placed in a press to remove any excess water. When the excess water is drained, the cassava flakes go through another grinding process to give it an even finer texture which then goes through a dryer. The dried cassava then finally goes through a hammer mill to produce cassava meal that is ready to be placed in bags. 10 ton of cassava roots produces about 2 tons of cassava meal. The dryer used has the capacity to produce 350kg of cassava meal per hour.

Read more...

MILL CONSTRUCTION PROGRESS

mill construction progress24 cover

 

The excavation of Pit E has been completed and the preparation of Pit A’s floor foundation is underway.

SILO CONSTRUCTION PROGRESS

silo construction4 cover

 

The silo construction is progressing fast, only 8 more rings to go on silo number 4.

HOUSING STRUCTURES

silo construction1 cover

 

House 2 of the housing structure is coming together, the trusses and septic tank is finished and all the windows have been built in.

Read more...

MILL CONSTRUCTION PROGRESS

mill construction progress6

 

The first phase of the mill construction has started.
The excavation of Pit A has been completed.

SILO CONSTRUCTION PROGRESS

silo construction1 cover

 

The silo construction is moving along swiftly and we are currently busy with the roof of silo number 4.

FRENCH JOURNALIST VISITS S.E. PARC AGRO

french journalist cover

 

Lauréne Senechal, a freelance journalist, recently paid a visit to the 80 000ha farm at S.E. Parc Agro Industriel, as she is making a documentary about this exciting initiative.

ON-SITE DEMONSTRATIONS

on site demo cover 7

 

A demonstration in progress where a silo bag, used for storing maize is being debulked into a trailer for use.

ONSITE DEMONSTRATIONS

onsite demo cover 6

 

In this demonstration, maize is moved from the debulking trailer after harvested into a silo bag where it is stored.

BEDNAR SWIFTERDISC

bednar swifterdisc cover 5

 

Ground preparation has never been this easy and accurate. Here you see one of the Parcs’ amazing Bednar Swifterdisc implement in action doing ground preparation.

FUEL POINT

fuel point cover 4

 

S.E. Parc Agro boasts with its own fuel point. Here we conveniently refill all our tractors, vehicles, moving equipment etc. This fuel point helps us to save on projects downtime that would have been caused by waiting for fuel.

EARTHMOVING EQUIPMENT

earthmoving cover 3

 

Earthmoving equipment used to move material for construction projects.

GREENHOUSES STRUCTURE CONSTRUCTION

greenhouse cover 2

 

Preparing irrigation in the greenhouses’ before installation can take place.

BRIDGE PROJECT

Bridge Project Cover 1

 

We are collecting and sorting preparation material for the current bridge project.

Read more...

CONSTRUCTION UPDATE ON THE HOSTELS

hostels cover 29

 

The main sewage line and septic tank for hostel 2 are almost completed.

WEIGHBRIDGE CONSTRUCTION PROGRESS

cover weighbridge const 3

 

We are carefully putting the weighbridge in place.

BRIDGE PROJECT

0095

 

Currently clearing the area where we will lay down the preparation material for the bridge project.

Read more...

BRIDGE PROJECT

 

We are also progressing with the bridge project. Currently, steelworks are being done.

Read more...

SILO CONSTRUCTION PROGRESS

silo construction 10

 

The last concrete was laid for silo 10.

SILO CONSTRUCTION PROGRESS

Silo 5 Cover2

 

Rooftop for silo 5 is complete.

SILO CONSTRUCTION PROGRESS

Silo 10 Cover

 

We are preparing for concrete work at silo 10.

SILO CONSTRUCTION PROGRESS

Silo 6 Cover

 

Next up, silo 6! We have started with the rooftop.

SILO CONSTRUCTION PROGRESS

Silo 9 Cover

 

Concrete works for silo 9 is finished.

SILO CONSTRUCTION PROGRESS

Silo 5 Cover

 

Rooftop construction on silo 5 is going well. As you can see it is growing quickly into a complete structure.

SILO CONSTRUCTION PROGRESS

Cover for silo 10

 

We are laying the concrete for silo 9.

SILO CONSTRUCTION PROGRESS

Cover for silo 9

 

Installing the steel fixtures for the silo 10 slab.

SILO CONSTRUCTION PROGRESS

Cover for silo 5

 

It’s happening! We are starting with the rooftop of silo 5.

GREENHOUSES STRUCTURE CONSTRUCTION

Cover vir local worker update

 

We are proud to have local workers on the Parc. Here’re a few of the guys busy fitting the water systems.

GREENHOUSES STRUCTURE CONSTRUCTION

Cover vir 3 greenhouses update

 

3 Greenhouses are covered with plastic. During the coming week, all of the structures will be covered with plastic and shade cloth.

SILO CONSTRUCTION PROGRESS

Silo cover update

 

The first 2 wet and dry bins of the silo complex are complete. They are a staggering 14 metres at their highest point. The third one will be completed in the current week.

SILO CONSTRUCTION PROGRESS

Silo 10 filling stage

 

The filling stage for silo 10 is nearly complete and preparation will start soon for laying the final concrete slab.

SILO CONSTRUCTION PROGRESS

Slab prep complete

 

Slab preparation is complete and we are ready to lay the concrete.

SILO CONSTRUCTION PROGRESS

Silo 3 cover

 

The roof on silo 3 is complete and we have installed the lifting jacks.

WEIGHBRIDGE CONSTRUCTION PROGRESS

Weigh Construct cOVER

 

Weighbridge foundation and slab completed, as well as the weighbridge room and computer room. Installation of the electrical cables is in progress.

SILO CONSTRUCTION PROGRESS

Silo Construt Cover

 

Almost finished with the second silo shell. We are installing the last ring of the silo. After we’ve finished this silo we will begin completing the third silo shell. We are also building foundations for the blowers and fans of these silos’.

GREENHOUSES STRUCTURE CONSTRUCTION

Greenhouse Struct cOVER

 

We have started to fit the plastic covers on the first greenhouses.

GREENHOUSES STRUCTURE CONSTRUCTION

GreenHouse Cover2

 

We are busy fitting the lock profiles that will hold the plastic in place over the greenhouses structure.

GREENHOUSES STRUCTURE CONSTRUCTION

GreenHouse2 Cover

 

7 houses today! We are busy cementing down the posts fort the last greenhouses structure.

CONSTRUCTION UPDATE ON THE HOSTELS

Hostels Hooffoto

 

Hostel 3 has been completed. All three completed hostels are currently being occupied.

GREENHOUSES STRUCTURE CONSTRUCTION

Greenhouses Hooffoto

 

5 down 7 to go! Five of the tunnels have been completed and preparation to put the plastic up has commenced. Once the plastic covering has been added, installation of the irrigation pipes will start.

SILO CONSTRUCTION PROGRESS

Silo Hooffoto

 

Only one more ring to fit to complete the first drying bin.

CASSAVA FACTORY CONSTRUCTION

Construction Cassava

 

The cassava cake receiving chamber and heat converter with cyclone and cooling towers are currently being installed. Getting us closer to the first life run of this factory.

SILO CONSTRUCTION PROGRESS

Silo Construction

 

Another silo base was finished and we still have two more to fully complete.

CASSAVA FACTORY CONSTRUCTION

Cassava Factory

 

Currently, we are installing the cassava flash dryer. This is done by a specialised team under the supervision of IITA.

WEIGHBRIDGE CONSTRUCTION PROGRESS

Weighbridge Concrete.1

 

Construction of the weighbridge is going well we will lay the concrete base in the coming week.

MILL CONSTRUCTION PROGRESS

Mill Construction Progress

 

The base foundation will soon be finished for our new mill. Construction will start in the coming weeks.

STONE CRUSHING PLANT PRODUCTION

Stone crushing plant production

 

Crushing plant running full production to supply the builders with the needed sand and stone for building

CONSTRUCTION UPDATE ON THE HOSTELS

Construction Updates on Hostel 3 3

 

Hostel 3 is finished and can be occupied from this coming weekend. This hostel will be able to accommodate 6 people.

SILO CONSTRUCTION PROGRESS

silo construction0064

 

Two silo foundations still in progress, to finish we still need to do the final brickwork and back filling.

WEIGHBRIDGE CONSTRUCTION PROGRESS

Construction of Weighbridge Structure stared

 

Weighbridge foundation in progress, with the start of construction on the bridge structure.

CASSAVA FACTORY CONSTRUCTION STILL UNDERWAY

Cassava Factory

 
 

CONSTRUCTION UPDATE ON THE HOSTELS

Construction Updates on Hostel 3 2

 

Hostel 4 boast with great progress that includes electricity, plumbing, aircon, and beds. We are close to completion and will be able to offer 6 more rooms for boarding.

CONSTRUCTION UPDATE ON THE HOSTELS

Construction Updates on Hostel 3 1

 

We are nearing the completion of Hostel 3. The plumbing for this hostel is on its way from Kinshasa.

CEREMONY HELD TO CELEBRATE THE TURNING ON OF POWER

CeremonyCover

 

On the 21st of April 2016, a ceremony was held about 60km from Mongata. The Chief advisor to the Minister of Agriculture graciously opened the ceremony for one of the most important achievements this year at Parc Agro. For more view pictures of this day in our gallery under “TURNING ON POWER CEREMONY”

Read more...

AFRICAN DEVELOPMENT BANK GROUP VISITS S.E. DU PARC AGRO

AfricanCover

 

We were very excited to welcome the African Development Bank Group at S.E. du Parc Agro. During their visit, we took them on a tour around the farm. We visited the silo complex and feeder factory and showed them where the harvested grains will be temporarily stored. We went to the cassava cultivation area and explained the growing process. Other areas we went to include the pivot dam, power station, and accommodation complex. Please go to our gallery to view the photo’s from the visit.

Read more...

NEW EQUIPMENT ARRIVE FOR QUARRY WORK

NewEquipmentCover

 

A new EDT Hydraulic Breaker arrived at the park. This machine is fitted on to the SLDG 30 ton excavator. It is used to break the stones that come out of the quarry into more manageable pieces for the stone crushing plant.

PROGRESS ON THE FIRST HOSTEL

HostelCover

 

We are very excited to say that we are busy with the final work on the first hostel. Please take a look at the images in our gallery under Housing Structure.

BEDNAR ATLAS HO LAUNCHED IN DRC

 

Bednar machinery connects into a large government project with implements to maintain the new arable area in Parc Agro Bukanga-Lonzo. The project will be running in 3 phases over 80 000 ha, in which 3000 ha as the first arable area and 1600 ha under irrigation. The total arable area is expected to reach up to 20 000 ha. The remainder will be used for fruit and nut planting, housing structures, schools, power plant, water reservoirs, dam, grain silos, roads, industrial zone etc. This project has been running for 3 years with around 500 workers.

Read more...

SILO COMPLEX PROGRESSING

Silo Cover 2

 

When completed harvested maize will be stored here for later use and distribution after each harvest season

BIRDS EYE VIEW OF THE WORKSHOPS AND WAREHOUSES

Logistics Cover

 
 

RIVER FLIGHT AND PUMP STATION PROGRESS

Cover River

 

After completion, it will be used to take water further up to two large lined dams from where it will supply water to facilities on the farm

PIVOT DAM PROGRESS

Pivot Dam Cover

 

After completion water from the river will be stored in a riverside reservoir for further distribution to the central pivot irrigation system

PREPERARING THE PIVOT LANDS FOR COVER CROPS

Pivot Lands Cover

 

We are currently preparing the pivot lands for planting cover crops. Cover crops are crops planted primarily to manage soil erosion, soil fertility, soil quality, water and weeds

GROWTH PROGRESS OF THE MAIZE WE PLANTED IN DECEMBER 2015

Cover Maize 2

 
 

GROWTH PROGRESS OF THE FIRST MAIZE WE PLANTED IN NOVEMBER 2015

Cover Maize

 
 

SUNDAY CHURCH AT THE PARC

ChurchCover

 

An informal church is held every Sunday at the Parc. A temporary structure is used as a church where sermons are given and people can come together in prayer. We are currently in the progress of building a church on the Parc

Read more...

PREMATURE VISITS S.E. PARC AGRO

CoverVisits

 

The first team from Premature came to visit the Parc during the month of December 2015. There was about 35 people who attended. During the visit we took them on a tour to see what exactly we’ve been up-to and the progress that we have made since we started this project. We took them to see the construction taking place of the Pivot Dam, Power Station, Flight Pump Station at the Kwango river and the Silo Complex to name but a few. We also showed them the Quarry and Stone Crushing Plant in action. The visitors was in total disbelief that the project was still so young and that we were only busy for little more than a year since the equipment and material arrived. Some of the visitors went to the Church on the Parc and prayed for the project, we were overwhelmed by this kind gesture from them. May God bless them and this project.

Read more...

WEIGHT BRIDGE CONSTRUCTION

WeighBridge Cover

 

One of our current project on the park is a weight bridge. This will have multiple uses, but mainly will help with weighing the harvested products. We have currently finished the foundation for the weight bridge as seen on the photo. More updates will follow.

Read more...

GRAIN STORAGE (SILO COMPLEX) CONSTRUCTION UNDERWAY

COVER

 

The silo complex construction continues. Concrete works in the receiving pits as well as the first and second elevation pits are finished. The foundations are laid out and finished for the silos’ right hand side of the dryer as well as the right sides cooling compartments.

Read more...

BEDNAR ATLAS HO 8000

Bednar Atlas HO

 

As you have seen on a previous news flash, we were very excited to share that the S.E. Parc Agro farm received Bednar Impliments (Atlas HO 8000) for the 2015 planting season. We felt that because we are so impressed with the Bednar Atlaas HO 8000, we wanted to tell you a bit more about how it. This specific implement, the Bednar Atlas HO is a heavy, compact, short disc cultivator, designed for stubble cultivation up to 18 cm. It boasts a Cross Control system to regulate the front disc row working angle. Also an integrated axle for excellent stability even at high speeds and small turn radius. There is also a Twin Disc System that ensures a high material throughput. To view a short demonstration of the Atlas HO visit our Gallery Video section.

Read more...

STUNNING MAIZE CROPS FOR 2015

banner 03 785cd0e9fa

 

Very blessed and proud to be able to say that the maize crops for the 2015 season surpassed our expectations.

MAIN PIVOT - PUMP STATION PLANS

MAIN PIVOT PUMP STATION PLANS

 
 

EXCAVATION OF PIVOT DAM

EXCUVATION OF PIVOT DAM

 

Another 1,5 m needs to be dropped, that is about 170 000,00 cubic meters of soil that we still need to excavate before we reach the desired depth for the pivot dam. As of yet we are about 40% away from completion.

ONE OF THE 1 000 m² WAREHOUSES ARE NEAR COMPLETION, WITH A 4th ONE STILL IN PROGRESS

ONE OF THE 1000M

 
 

MAIN PUMP STATION PROGRESS

MAIN PUMP STATION PROGRESS

 
 

PIVOT WATERLINES AND ELECTRICAL CABLES BEING LAID OUT

PIVOT WATERLINES

 
 

FLIGHT PUMP STATION LINE

FLIGHT PUMP STATION LINE

 

Containers arrive on the Parc with the pipes that will be used for the flight pump station line

SUMP SECTION OF THE FLIGHT PUMP STATION COMPLETED

SUMP SECTION OF THE FLIGHT PUMP STATION

 
 

CONSTRUCTION OF CASSAVA PLANT WAREHOUSE

CASAVA PROJECT WAREHOUSE

 

Construction of the first cassava warehouse has started. This warehouse will be used by the cassava processing factory

SECOND BLOCK OF MAIZE

SECOND BLOCK OF MAIZE

 

We started with the second maize block. As seen in the photograph the first block is on the left and second on the right. Follow the growth in our gallery under Maize progress 2015 season

GROWTH PROGRESS OF THE FIRST MAIZE BLOCK PLANTED FOR THE 2015 SEASON

MAIZE PROGRESS 2015

 
 

MINISTER OF AGRICULTURE PAYS A VISIT TO S.E. PARC AGRO

Minister Cover

 

S.E. Parc Agro was very excited to have the Minister of Agriculture ( Emile Christophe Mota Ndongo) visit the parc and see first-hand the great work and progress done each day. During his visit he was accompanied by Mr. de Melim (Operations Director) and other officials on a detailed tour of the grounds. The tour included the Cassava and Maize lands, Power station, Quarry, Workshops, Warehouses and Hostels’ to name but a few. More about this visit in our gallery

Read more...

MAIZE AND FLOUR DISTRIBUTION

Maize Flour Group

 

The distribution of Maize and Flour has commenced. The available products include: 10 kg and 25 kg Natural White Maize Flour; 10 kg and 25 kg Natural Yellow Maize Flour; 50 kg Natural White Maize; and 50 kg Natural Yellow Maize. The Maize and Flour products are proud products of S.E. Parc Agro du Bukanga-Lonzo and are being distributed among the locals.

Read more...

BUHLER VERSATILE TRACTORS AND NEW BEDNAR EQUIPMENT READY TO START WORKING

Cover bednarBuhler

 
 

FLIGHT PUMP STATION TAKING SHAPE

Cover Flight

 
 

Casting of the walls have started for the maize receiving pit

Cover Silo progress 2

 
 

POWERLINE CONSTRUCTION

Cover Powerline

 

Powerline construction is progressing according to the set timeline. We hope to start fitting the overhead cables from the 1st of October 2015

PIVOT DAM CONSTRUCTION UNDER WAY

Cover Pivot Dam

 

We are busy clearing soil so that we get to the correct depth for the pivot dam. Pipes will run from the dam to the pivots with the needed water supply

NEW CENTRAL GENERATOR SITE

Cover New Generator

 

Construction has begun on a new Central Generator Site. Soon there will only be one generator on the Park supplying electricity to all the different section of the Park

WATER AND ELECTRICITY TRENCH BEING LAID OUT TOWARDS THE HOSTEL AND OTHER HOUSING STRUCTURES

Cover Water And Elec

 
 

Read more...

THE FLIGHT PUMP STATION CONSTRUCTION IS PROGRESSING NICELY

Cover Pump Station

 
 

The silo construction from a birds eye view

IMG 20150917 WA0011

 
 

THE FIRST MAÏS DE BUKANGA-LONZO CONTAINER STORE IN MUSINA

Cover Musina

 

The first Container Store has been placed in Musina. Here the maize that was planted and harvested on the S.E. Parc Agro site will be sold. This is a great achievement, the product was 100% locally produced in the DRC and we thank everyone that helped to make this possible.

Read more...

MAIN ENTRANCE PREPARATIONS HAS BEGUN

Cover Entrance2

 

The first groundworks has begun for the new entrance. We will keep you up to date with the latest development

S.E. DU PARC AGRO MAIN ENTRANCE

Cover Entrance

 

Sneak peak of the main entrance that will be built at S.E. du Parc Agro

MAÏZ DE BUKANGA-LONZO CONTAINER STORES IN PROGRESS

Cover Container Stores

 

You have seen the advertisement, now you get to see a sneak peak of the new Container Stores that will be selling “MAÏZ DE BUKANGA-LONZO”. The first store is almost ready to be revealed. We will be posting this event tomorrow on our website with media links, as well as on the Facebook site.

Read more...

BEDNAR ATLAS HO8000 ARRIVES AT S.E. PARC AGRO

Cover Bednar

 

The first Bednar Atlas HO8000 arrived at the Parc today in 3 containers

SILO PROGRESS

Cover Silo Progress

 

Please follow the silo progress in the gallery under “SILO COMPLEX CONSTRUCTION IS COMING ON NICELY”

New Cellular Tower

Cover Cellular Tower

 

Vodacom erected a new cellular tower on the S.E. Parc. It went live on the 5th of September 2015

MAIN ENTRANCE PROJECT

 MAIN ENTRANCE PROJECT

 

Discussion for the Main Entrance has started. We will start with this new and exciting project very soon

CASAVA PROJECT IN FULL STEAM

Cover Casava projects

 
 

AIRCRAFT HANGAR COMPLETED

Cover Aircraft

 
 

EXCAVATION OF THE RIVER FLIGHT PUMP STATION

Cover excavation

 

Excavation of the river flight pump station begun on the 27th of August at 9h00. Yesterday they reached the required depth of 3,5 meters below the river level. Luckily there was no water filtration and everything went according to plan

Read more...

silo complex construction is coming on nicely

Cover Silos

 

NEW TELEVISION ADVERT FOR MAÏZ DE BUKANGA-LONZO

Cover 3

 

The new television advert for Maïz de Bukanga-Lonzo aired yesterday in the RDC. The maize for this meal was planted and harvested locally at S.E. du Parc Agro. After harvesting it was transported to the milling plant in C.D.I.-Bwamanda Kinshasa, where it was processed and sacked for distribution. We thank each and every one who helped to make this happen. We are all very proud and honoured to be a part of this.

Read more...

PVC PIPE PRODUCTION STILL GOING STRONG

Cover

 

2 500 meters of PVC Tubing produced for the past week

BUHLER VERSATILE TRACTORS ARRIVE IN MATADI

Buhler

 

We are excited to share with you that the Buhler Versatile Tractors that left South Africa a few months back have arrived. Two of the tractors are already loaded and on their way to the “Parc” in Bukanga-Lonzo

MANUFACTURING PVC PIPES LOCALLY

Cover2

 

During the past few weeks we have been busy setting up to produce our own PVC pipes. To be able to do it ourselves locally, is a great achievement. We produced 560 meters of pipe with measurements of 50 mm x 5 mm in a mere 24 hour run. Everyone on the “Parc” is very excited and proud of this operation.

Read more...

OUR NEW FACEBOOK PAGE

Facebook

 

We are proud to say that we have entered the social media scene with a new Facebook page. Come browse through our page, like and share with friends and family. Find us “S.E. Parc Agro Industriel de Bukanga-Lonzo”

HOSTEL PROGRESS

Hostel Progress

 

The first two hostels are practically finished. Final touches like air conditioning, showers, water and electricity supply will be attended to in the coming weeks. Construction on hostel three and four will commence on Friday. We will keep you up to date.

Read more...

LOGISTICS

Logistics

 

Three of our JAC trucks will transport 60 tons of maize to the mills in Kinshasa. Afterwards they will return with approximately 90 tons of lime to the farm

BRICK PRODUCTION

Brick Production

 

We produce about 500 bricks per day these are used for construction purposes

NEW WAREHOUSES

New Warehouses

 

Construction of warehouses are progressing fast. Each warehouse is approximately 600 m2 and will be finished by next week

AIRCRAFT HANGAR NEAR COMPLETION

Airplane Hangar

 

We are excited to say that construction is near completion. Only cladding on one side remains and instillation of the hangar doors

THE FIRST GREEN PEPPERS PICKED

IMG 20150812 WA0001

 

The first green peppers were picked from the local vegetable garden on the site. This gives hope to those in the area for fresh, locally grown products. For most of them these are the first vegetables they have ever eaten

Read more...

NEW GRAIN STORAGE FACILITY READY FOR CONCRETE WORKS

0002resized

 

Construction is moving along swiftly with the first silo ready for concrete work. We willkeep you updated with the progress, in the meantime you can view images in the Gallery section under Construction of the Grain Storage Facility.

Read more...

Bucket elevator pit and conveyor trench at the Silo Site

IMG 20150729 WA0004

 
 

Construction continues swiftly for the other Housing Structures

Housing Construction 1.2

 

Read more...

Construction of Community Centre well in progress

Construction_of_Community_Centre_in_Progress

 

Read more...

Mechanical Workshop finished

Mechanical_Workshop_Finished.jpg

 

Here all the repairs and maintenance will be done on mechanical equipment. Practical training will also be held here in various mechanical areas to better equipped the workers with the right skills for the trade

Read more...

First water Reservoir finished and filled with water

First Water Reservoir Finished and filled with water2

 

This reservoir will be used with others to supply water for building and farming purposes

Read more...

Construction on S.E. Parc Agro Booming

IMG 20141027 WA0078

 

The past few weeks’ construction on S.E. Parc Agro has been booming. So much progress has been made, from the construction of several Housing Structures, a Medical Clinic, Mechanical Workshop and even a new Airplane Hangar.

Read more...

S.E. PARC AGRO DEVELOPMENT NEWS

IMG 20150522 WA0026

 

Yet another function has been added to the already extensive S.E. Parc Agro Development in the form of a milling plant in C.D.I.-Bwamanda Kinshasa. Harvested maize crops from S.E. Parc Agro are processed into maize meal and packaged to be sold to the local population.

Read more...

Ground preparation by applying TRIOMF Liquid Lime to the ground

Liquid Lime 1

 

Currently on the park we are busy drying maize that's been harvested the past few weeks

Read more...

A new combine table has arrived

New Combine table

 

This table is specifically used for soy and dry beans

Read more...

The electrical substation at S.E. Parc Agro is taking form

Electrical Sub 1

 

Read more...

Official Ground Breaking Day

10Edited

 

The 7th of May 2015 marked the official Ground Breaking Day at the site of the Marché International de Kinshasa. Fresh produce such as vegetables, grains, meat and fruit, will in future, be supplied here from S.E. Parc Agro Industriel de Bukanga-Lonzo daily to Marché International de Kinshasa. The new Marché International de Kinshasa will house large volumes of fresh products creating a platform for fresh produce trading. High-level commercial food trading principles at a domestic and international level will be active within Market incorporating E-commerce through a complex web-based trading system. Price regulations and benchmarks will control both the local and export markets. Daily auctions will be held. This market concept will create a very affordable basis for locally produced food products. For more about Marché International de Kinshasa please follow the link click on the following link kinfrais.com

Read more...

Maize Drying and Storage

 drying maize that’s been harvested

 

Currently on the park we are busy drying maize that’s been harvested the past few weeks. Maize go through this process if the moisture percentage is too high for storage. After the drying process the maize is stored in silo bags

Read more...

An additional project under consideration by S.E. Parc Agro

 

An additional project under consideration by S.E. Parc Agro is the bottling of fountain water to market to the public. This is a 3D illustration of the proposed bottle and packaging to be used

Read more...

Harvesting and Ground Preparations

harvesting

 

We are currently busy with harvesting as well as new ground preparations

Read more...

Beijing China arrived at S.E. Parc Agro

IMG-20150424-WA0031

 

On the 15th of April three employees from SDLG (Shandong Lingong Construction Machinery CO. LTD), Beijing China arrived at S.E. Parc Agro. One of these employees will stay till the 30th of April to give intensive technical training in all the SDLG equipment such as Excavators,Wheel loaders, MT60 Dumper trucks and LTB's. After the training the local mechanics should be able to do proper diagnostics and repair on all the above mentioned equipment.

Read more...

first trial of beans

first trail of beans

 

During the month of March, S.E. Parc Agro planted their first trial of beans. A total of 80 hectare Soy beans and 15 hectare Dry beans were planted. The result of the trial will determine if the Park is suitable for this selection of crops. Here is a picture taken on the 3rd of April.

Read more...

FARMERS BUCKETS

Farmers Bucket

 

As part of TRIOMF's venture in the Democratic Republic of Congo, which aims to eradicate the high costs involved with importing fertilizer, creating employment and ultimately building the industry as a whole, the concept of a "Farmers Bucket" was introduced.

Read more...

CEO of Africom Commodities Christo Grobler's Harvest Day Speech

 

 
 

Read more...

Buhler Versatile Tractors soon to arrive at Parc Agro

 

S.E. Parc Agro will soon boast with new Buhler Versatile Tractors. These tractors are all 4WD (four wheel drive). They are very well-built as well as extremely reliable.

Read more...

HARVEST DAY

Breaking news

 

S.E. Parc Agro Industriel de Bukanga-Lonzo, hosted its first ever harvest day on Thursday, 5 March 2015. This event was welcomed with great excitement and interest. The day was filled with different demonstrations, maize trials and lectures as well as a sneak peak of Season B's plan- tations. The day's events were high- lighted with the active participation of his excellency the President by har- vesting a section of maize crops, to the delight of the crowd.

Read more...

FIRST STAGE OF EARTHWORK

FIRST STAGE OF EARTHWORK

 

As can be seen in the photographs, the first stage of earthworks for the construction of the grain storage facility is in full swing. The soil is in the process of being taken away to ensure that the base on which the grain silos will be built on, is levelled out. The exact location of the storage facilities has been strategically identified as per soil surveys conducted which will help in reducing travelling time from the fields to the silos. Another advantage is the quicker and more effective means of distribution as from the farm to the milling factory markets, further contributing to the ease in solving the grain storage and handling needs of farmers in the Bukanga-Lonzo area.

Read more...

A temporary structure is being built to serve as a bridge

 
 

Read more...

Preparations have started for the first Silos to be built

 

Read more...

Mission accomplished for Haevic

Haevic__Parc_Agro

 

Anyone who has been fortunate enough to experience the "S.E. Parc Agro Industriel' initiative in the district of Bukanga-Lonzo first hand share one common fascination ... the sheer size of it all.

Read more...

First 5 000 ha

000 5000 ha Progress 02

 

We are very satisfied with the progress of the first 5 000 ha

Read more...

Navigation System

 

A very sophisticated navigation system is being installed into one of the Air Tractors

Read more...

Second Air Tractor

 

The second Air Tractor has arrived at N'djili Airport Kinshasa

BBC News

BBC News 3D English

 

African soil crisis threatens food security, says study

Read more...

Visitors at Bukanga-Lonzo

Visitors

 

On the 6 of December 2014 very important guests visited the Park.The response was overwhelmingly positive about all the work that has been done.

Read more...

Wall Street Journal

Wall Street Journal 3D English

 

S.E. Parc Agro Industriel de Bukanga-Lonzo reaches international media

Read more...

5 000 ha maize

 

A total of 5 000 ha maize have been planted on the S.E. Parc Agro Industriel de Bukanga-Lonzo farm

CHURCH CONSTRUCTION

Photo 2014-10-21 9 12 38 PM

 

A cluster home development scheme has been launched. Well built, safe and pratical, yet aesthetically pleasing houses have been designed. Dwellings will comprise of two and three-bedroom options in various layouts. Landscaping and roads will provide comfort and a homely atmosphere. Incorporated into the housing development community facilities such as schools, a medical centre, a church plus recreational areas will be eagerly anticipated.

Read more...

Harvesters

Harvester

 

On 29 October 2014, two of the Challenger 540 Harvesters arrived on the farm. These robust, highly-regarded American harvesters will be deployed to harvest the large areas of plantations at timeous speeds. With various head-compatibility, the harvesters will initially be fitted with rugged South African produced equipment suitable for maize crop harvesting

Read more...

Church

church

 

During September 2014 the first bricks were placed to build the new Church. This place of worship will not only accommodate local people from the "Parc" and the area, but also national and international visitors.

Read more...

Medical Clinic

medical centre

 

In September 2014, the building of a complete and fully-equipped medical centre started. Here only the best personnel will be employed to deliver excellent and thorough medical care

Read more...

PLANTING 1 200 HA

First 1000Ha Planted

 

On the 22nd of September, perfectly timed according to schedule, history was made as the massive planting project at S.E. Parc Agro Industriel de Bukanga-Lonzo got underway. No less than twelve Equalizer Planters were pulled into action by twelve super powered Massey Ferguson 8690 tractors, to plant the first 1 200 hectares of plantations. With the amazing Equalizer 16-row Planters, a no-till principle is adopted for the effective, timeous mass cultivation of land.

Read more...

First Batch of Fertilizer Arrives on Farm

Fertilizer arrive on farm

 

Only the best in soil-preparation and fertilization products from TRIOMF FERTILIZER will be applied to various stages of the crops during the plant cycle. PoP-uP™, a growing medium will be used during planting is sufficient after soil preparation with Liquid Lime™. NitreX™ super urea, Politain™ microbial urea and Bakgat™ foliar feeds will be applied at specific intervals during the season. Carefully prescribed products and dosages will be formulated and applied according to the TRIOMF Agri Xcellence Agronomists' recommendations.

Read more...

Housing Development

Housing Development

 

A cluster home development scheme has been launched. Well built, safe and pratical, yet aesthetically pleasing houses have been designed. Dwellings will comprise of two and three-bedroom options in various layouts. Landscaping and roads will provide comfort and a homely atmosphere. Incorporated into the housing development community facilities such as schools, a medical centre, a church plus recreational areas will be eagerly anticipated.

Read more...

Logistics Buildings

Logistics Building

 

Two corrugated steel structures for the safe storing of 'inputs' such as fertilizer, seed, herbicides and pesticides. Tractors can also be stored when not in use

Launch of S.E. Parc Agro Industriel de Bukanga-Lonzo

Launch-new

 

Tuesday, the 15th of July 2014 marked the spectacular Media Launch of S.E. Parc Agro Industriel de Bukanga-Lonzo. At this historic event, the official opening of the first S.E. Parc Agro development at Bukanga-Lonzo took place in the presence of His Excellency Joseph Kabila Kabange, President of the DRC and other high-ranking officials. Attendees from the DRC Cabinet included His Excellency Matata Mponyo Mapon, the Prime Minister and other various Ministers.

Read more...

First Pivots Erected

Pivots

 

A large area of 20 ha x 50 ha has been demarcated for a central-pivot irrigation network for vegetable cultivation. These technologically advanced, automated central-pivots will supply water and fertilization to 1 000 ha crops. The irrigated area will finally consist of 20 large central-pivots. 4 500 000 million litres of water per hour will be administered to the fine selection of cultivars via a precision irrigation management system.

Read more...

Arrival of Air Tractors

Air Tractor

 

The AIR TRACTOR crop sprayer is a state-of-the-art aircraft imported from the USA. As the safest, most powerful and economic type in its class, the AIR TRACTOR is highly suited for aerial fertilization and pest control. One of these two agricultural aviation aircrafts are now stationed on a semi-permanent basis at S.E. Parc Agro de Bukanga-Lonzo and will also be available on rental for future projects in the DRC. Liquid and dry products will be provided as applications to crops by means of the AIR TRACTOR aircrafts.

Read more...

Air Strip

air strip

 

An aircraft landing strip is being cleared for the arrival of the first Air Tractor

Read more...

Cellular Receivers

Cellular Receiver

 

The erection of three cellular communication towers at strategic points

Read more...

Arrival of Planters

Arrival of Equilizer Planters

 

A fleet of 12 EQUALIZER planters arrived at S.E. Parc Agro de Bukanga-Lonzo. The EQUALIZER Min-Till Precision Wide span planter has been developed to plant row crops like maize, sunflower, soya beans, etc. in a single pass without any prior soil preparation through cultivation. Working through a parallel linkage, the planter places fertilizer and seed in the plant-row. This planter improves field productivity and reduces operational costs.

Read more...

Surveying of building positions

Surveying of building positions

 

A Team of Professionals are busy marking out stands for the positioning of the buildings and complexes that are to be erected.

Read more...

Roadworks

Road Works

 

Clearing and earth moving in preparation for a road network on the farm commenced which included the demarcation of roads from the entrance of S.E. Parc Agro de Bukanga-Lonzo across the entire farm to key-centres, plantations and service areas. This important and intricate initial phase of establishing access routes is vital to the timeous and successful development of the agricultural park and all of its facets. Like all projects on the farm, local labour and international skills are utilized.

Read more...

Employment of local people

First Local People Employed

 

One of the project's top priorities is to appoint local staff and allow them to develop job-specific skills. It was with great pleasure that we welcomed the first appointed locals to our workforce at S.E. Parc Agro Industriel de Bukanga-Lonzo months ago:

Read more...

Clearing of Vegetation

Clearing of Vegetation

 

Due to the dense vegetation close to the river, the development team has to first clear the area. This will be done from the river-front extending into the escarpment

Temporary living quarters

Temporary Living Quarters small

 

Special green containers arrived at the Parc. This will be changed into sleeping quarters and offices. The camp currently accommodates 18 people, but they are still busy transforming containers into living quarters

Arrival of First Equipment

First Equipment arrive

 

The Arrival of the Massey Ferguson tractor fleet marked a historic day at S.E. Parc Agro de Bukanga-Lonzo means now able to commence with serious earth-moving and ground preparation procedures. The work-horse fleet of 18 brand new Massey Ferguson machines consists of eight (8) MF 8690, four (4) MF 7618 and six (6) MF 480 tractors, and thirty-six (36) Tafe 8502 (4x4) tractors. These tractors will use custom implements such as ploughs, cultivators, transfer trailers, wagons, slashes and boom sprayers to more easily simplify the agricultural process at the farm.

Read more...

Civil Planners / Construction Specialists

civil planners

 

Land Surveyor - A Land Surveyor visited the site to accurately measure and produce relevant contour maps required for further (or more) land information. Detailed maps and images are now available.

Electrical Consultant - Electrical consultants advised on equipping the area with a complete electrical energy infrastructure solution.

Town Planner - The Town Planner was contracted to the site for the purpose of optimizing the effectiveness of the land-use and infrastructure.

Read more...

Agronomists

Agronomists

 

A team of South African qualified agriculturists and soil scientists were sent to the allocated site to test and map the area. Soil samples were sent to a laboratory in South Africa for analysis. Arable areas were identified and recorded. With the acquired data, the TRIOMF Agri Xcellence team of agronomists could accurately and effectively offer recommendations on suitable and economic grain varieties as well as other crop planting advice.

Read more...

Contractual Agreement

 

Upon the Government's initiative to develop Agricultural Business Parks, the first "S.E. Parc Agro Industriel" came straight off the drawing board. The Government of the Democratic Republic of Congo agreed terms with the South African Contractor to develop the allocated area at Bukanga-Lonzo as a complete and contained Agricultural centre.

Read more...

Follow Us @ Parcagro  |  facebook icon youtube icon #parcagro

FOLLOW US @ PARCAGRO  facebook iconyoutube icon
#PARCAGRO

Home
S.E. PARC AGRO INDUSTRIEL DE BUKANGA-LONZO
WELCOME TO THE EXCITING FUTURE OF S.E. PARC AGRO DE INDUSTRIEL – THE BRAND NEW AGRICULTURAL BUSINESS PARK CONCEPT UNIQUE TO THE DEMOCRATIC REPUBLIC OF CONGO
This first-of-its-kind DRC government initiative commenced early 2014 when a special agreement was reached to start the development of agricultural sectors throughout the country. S.E. Parc Agro Industriel is essentially a concept of agricultural land development with the implementation of the necessary infrastructure to support a self-sustained economic unit. This large scale implementation includes not only the best in plantations but also support structures such as roads, water supply, power lines, housing, hospitals and schools and even a landing strip for aircraft.
The first sector development under the new S.E. Parc Agro Industriel initiative will be at Bukanga-Lonzo. Please continue to explore the following pages for more detailed information about this world famous project.
The S.E. Parc agro family, S.E. du parc agro industriel de Bukanga-Lonzo, Marche international de Kinshasa, Parc Agro-Industriel de Bukanga-Lonzo
ABOUT US
The Agricultural Business Park of the Democratic Republic of the Congo was the first step to a great agricultural reform in terms of the thought processes in Central Africa towards the development of agriculture. The first phase of the Agricultural Business Park is focused on basic crop production (maize). Maize production is unique in that it forms the basis of nutrition for not only humans, but also animals. The production of maize in phase one will therefore form the basis for future animal feed production. Bearing in mind that the main focus is not only creating, a stable agricultural and farming industry but also a sustainable chain of production i.e. from the planting of the basis material (raw material in the form of maize) right through to the final product being a piece of meat in the form of chicken on the consumers’ table.
The first sector development under the new "S.E. Parc Agro Industriel" initiative has commenced in the district of Bukanga-Lonzo, some 260 km South-East of Kinshasa. This 80 000 ha farm and village development offers a new challenge, the first in Africa, of accomplishing the goal of using raw prime land to maximum advantage for all concerned.
Other sectors will follow the pilot project of Bukanga-Lonzo. Other land will be developed not only for effective farming, but also for livestock farming plus several villages all equipped with electricity, and also comprising all the necessary modern day living requirements such as schools, clinics, libraries to maintain this new development from the raw earth.
WEIGHBRIDGE CONSTRUCTION PROGRESS

Weighbridge foundation and slab completed, as well as the weighbridge room and computer room. Installation of the electrical cables is in progress.
SILO CONSTRUCTION PROGRESS

Almost finished with the second silo shell. We are installing the last ring of the silo. After we’ve finished this silo we will begin completing the third silo shell. We are also building foundations for the blowers and fans of these silos’.
GREENHOUSE STRUCTURE CONSTRUCTION
We have started to fit the plastic covers on the first greenhouse.
GREENHOUSE STRUCTURE CONSTRUCTION
We are busy fitting the lock profiles that will hold the plastic in place over the greenhouse structure.
GREENHOUSE STRUCTURE CONSTRUCTION
7 houses today! We are busy cementing down the posts fort the last greenhouse structure.
CONSTRUCTION UPDATE ON THE HOSTELS
Hostel 3 has been completed. All three completed hostels are currently being occupied.
GREENHOUSE STRUCTURE CONSTRUCTION
5 down 7 to go! Five of the tunnels have been completed and preparation to put the plastic up has commenced. Once the plastic covering has been added, installation of the irrigation pipes will start.
SILO CONSTRUCTION PROGRESS
Only one more ring to fit to complete the first drying bin.
CASSAVA FACTORY CONSTRUCTION
The cassava cake receiving chamber and heat converter with cyclone and cooling towers are currently being installed. Getting us closer to the first life run of this factory.
SILO CONSTRUCTION PROGRESS
Another silo base was finished and we still have two more to fully complete.
CASSAVA FACTORY CONSTRUCTION
Currently, we are installing the cassava flash dryer. This is done by a specialised team under the supervision of IITA.
WEIGHBRIDGE CONSTRUCTION PROGRESS
Construction of the weighbridge is going well we will lay the concrete base in the coming week.
MILL CONSTRUCTION PROGRESS
The base foundation will soon be finished for our new mill. Construction will start in the coming weeks.

STONE CRUSHING PLANT PRODUCTION
Crushing plant running full production to supply the builders with the needed sand and stone for building
CONSTRUCTION UPDATE ON THE HOSTELS
Hostel 3 is finished and can be occupied from this coming weekend. This hostel will be able to accommodate 6 people.
SILO CONSTRUCTION PROGRESS
Two silo foundations still in progress, to finish we still need to do the final brickwork and back filling.
WEIGHBRIDGE CONSTRUCTION PROGRESS
Weighbridge foundation in progress, with the start of construction on the bridge structure.
CASSAVA FACTORY CONSTRUCTION STILL UNDERWAY
CONSTRUCTION UPDATE ON THE HOSTELS
Hostel 4 boast with great progress that includes electricity, plumbing, aircon, and beds. We are close to completion and will be able to offer 6 more rooms for boarding.
CONSTRUCTION UPDATE ON THE HOSTELS
We are nearing the completion of Hostel 3. The plumbing for this hostel is on its way from Kinshasa.
CEREMONY HELD TO CELEBRATE THE TURNING ON OF POWER
On the 21st of April 2016, a ceremony was held about 60km from Mongata. The Chief advisor to the Minister of Agriculture graciously opened the ceremony for one of the most important achievements this year at Parc Agro. For more view pictures of this day in our gallery under “TURNING ON POWER CEREMONY”
AFRICAN DEVELOPMENT BANK GROUP VISITS S.E. DU PARC AGRO
We were very excited to welcome the African Development Bank Group at S.E. du Parc Agro. During their visit, we took them on a tour around the farm. We visited the silo complex and feeder factory and showed them where the harvested grains will be temporarily stored. We went to the cassava cultivation area and explained the growing process. Other areas we went to include the pivot dam, power station, and accommodation complex. Please go to our gallery to view the photo’s from the visit.
NEW EQUIPMENT ARRIVE FOR QUARRY WORK
A new EDT Hydraulic Breaker arrived at the park. This machine is fitted on to the SLDG 30 ton excavator. It is used to break the stones that come out of the quarry into more manageable pieces for the stone crushing plant.
PROGRESS ON THE FIRST HOSTEL
We are very excited to say that we are busy with the final work on the first hostel. Please take a look at the images in our gallery under Housing Structure.

PROJECT SUMMARY
BEDNAR ATLAS HO LAUNCHED IN DRC
Bednar machinery connects into a large government project with implements to maintain the new arable area in Parc Agro Bukanga-Lonzo. The project will be running in 3 phases over 80 000 ha, in which 3000 ha as the first arable area and 1600 ha under irrigation. The total arable area is expected to reach up to 20 000 ha. The remainder will be used for fruit and nut planting, housing structures, schools, power plant, water reservoirs, dam, grain silos, roads, industrial zone etc. This project has been running for 3 years with around 500 workers.
SILO COMPLEX PROGRESSING
When completed harvested maize will be stored here for later use and distribution after each harvest season
BIRDS EYE VIEW OF THE WORKSHOPS AND WAREHOUSES
RIVER FLIGHT AND PUMP STATION PROGRESS
After completion, it will be used to take water further up to two large lined dams from where it will supply water to facilities on the farm
PIVOT DAM PROGRESS
After completion water from the river will be stored in a riverside reservoir for further distribution to the central pivot irrigation system
PREPERARING THE PIVOT LANDS FOR COVER CROPS
We are currently preparing the pivot lands for planting cover crops. Cover crops are crops planted primarily to manage soil erosion, soil fertility, soil quality, water and weeds
GROWTH PROGRESS OF THE MAIZE WE PLANTED IN DECEMBER 2015
GROWTH PROGRESS OF THE FIRST MAIZE WE PLANTED IN NOVEMBER 2015
SUNDAY CHURCH AT THE PARC
An informal church is held every Sunday at the Parc. A temporary structure is used as a church where sermons are given and people can come together in prayer. We are currently in the progress of building a church on the Parc
PREMATURE VISITS S.E. PARC AGRO
The first team from Premature came to visit the Parc during the month of December 2015. There was about 35 people who attended. During the visit we took them on a tour to see what exactly we’ve been up-to and the progress that we have made since we started this project. We took them to see the construction taking place of the Pivot Dam, Power Station, Flight Pump Station at the Kwango river and the Silo Complex to name but a few. We also showed them the Quarry and Stone Crushing Plant in action. The visitors was in total disbelief that the project was still so young and that we were only busy for little more than a year since the equipment and material arrived. Some of the visitors went to the Church on the Parc and prayed for the project, we were overwhelmed by this kind gesture from them. May God bless them and this project.

WEIGHT BRIDGE CONSTRUCTION
One of our current project on the park is a weight bridge. This will have multiple uses, but mainly will help with weighing the harvested products. We have currently finished the foundation for the weight bridge as seen on the photo. More updates will follow.
GRAIN STORAGE (SILO COMPLEX) CONSTRUCTION UNDERWAY
The silo complex construction continues. Concrete works in the receiving pits as well as the first and second elevation pits are finished. The foundations are laid out and finished for the silos’ right hand side of the dryer as well as the right sides cooling compartments.
BEDNAR ATLAS HO 8000
As you have seen on a previous news flash, we were very excited to share that the S.E. Parc Agro farm received Bednar Impliments (Atlas HO 8000) for the 2015 planting season. We felt that because we are so impressed with the Bednar Atlaas HO 8000, we wanted to tell you a bit more about how it. This specific implement, the Bednar Atlas HO is a heavy, compact, short disc cultivator, designed for stubble cultivation up to 18 cm. It boasts a Cross Control system to regulate the front disc row working angle. Also an integrated axle for excellent stability even at high speeds and small turn radius. There is also a Twin Disc System that ensures a high material throughput. To view a short demonstration of the Atlas HO visit our Gallery Video section.
STUNNING MAIZE CROPS FOR 2015
Very blessed and proud to be able to say that the maize crops for the 2015 season surpassed our expectations.
MAIN PIVOT - PUMP STATION PLANS
EXCAVATION OF PIVOT DAM
Another 1,5 m needs to be dropped, that is about 170 000,00 cubic meters of soil that we still need to excavate before we reach the desired depth for the pivot dam. As of yet we are about 40% away from completion.
ONE OF THE 1 000 M² WAREHOUSES ARE NEAR COMPLETION, WITH A 4TH ONE STILL IN PROGRESS
MAIN PUMP STATION PROGRESS
PIVOT WATERLINES AND ELECTRICAL CABLES BEING LAID OUT
FLIGHT PUMP STATION LINE
Containers arrive on the Parc with the pipes that will be used for the flight pump station line
SUMP SECTION OF THE FLIGHT PUMP STATION COMPLETED
CONSTRUCTION OF CASSAVA PLANT WAREHOUSE
Construction of the first cassava warehouse has started. This warehouse will be used by the cassava processing factory

SECOND BLOCK OF MAIZE
We started with the second maize block. As seen in the photograph the first block is on the left and second on the right. Follow the growth in our gallery under Maize progress 2015 season
GROWTH PROGRESS OF THE FIRST MAIZE BLOCK PLANTED FOR THE 2015 SEASON
MINISTER OF AGRICULTURE PAYS A VISIT TO S.E. PARC AGRO
S.E. Parc Agro was very excited to have the Minister of Agriculture ( Emile Christophe Mota Ndongo) visit the parc and see first-hand the great work and progress done each day. During his visit he was accompanied by Mr. de Melim (Operations Director) and other officials on a detailed tour of the grounds. The tour included the Cassava and Maize lands, Power station, Quarry, Workshops, Warehouses and Hostels’ to name but a few. More about this visit in our gallery
MAIZE AND FLOUR DISTRIBUTION
The distribution of Maize and Flour has commenced. The available products include: 10 kg and 25 kg Natural White Maize Flour; 10 kg and 25 kg Natural Yellow Maize Flour; 50 kg Natural White Maize; and 50 kg Natural Yellow Maize. The Maize and Flour products are proud products of S.E. Parc Agro du Bukanga-Lonzo and are being distributed among the locals.
BUHLER VERSATILE TRACTORS AND NEW BEDNAR EQUIPMENT READY TO START WORKING
FLIGHT PUMP STATION TAKING SHAPE
CASTING OF THE WALLS HAVE STARTED FOR THE MAIZE RECEIVING PIT
POWERLINE CONSTRUCTION
Powerline construction is progressing according to the set timeline. We hope to start fitting the overhead cables from the 1st of October 2015
PIVOT DAM CONSTRUCTION UNDER WAY
We are busy clearing soil so that we get to the correct depth for the pivot dam. Pipes will run from the dam to the pivots with the needed water supply
NEW CENTRAL GENERATOR SITE
Construction has begun on a new Central Generator Site. Soon there will only be one generator on the Park supplying electricity to all the different section of the Park
WATER AND ELECTRICITY TRENCH BEING LAID OUT TOWARDS THE HOSTEL AND OTHER HOUSING STRUCTURES
THE FLIGHT PUMP STATION CONSTRUCTION IS PROGRESSING NICELY
THE SILO CONSTRUCTION FROM A BIRDS EYE VIEW

THE FIRST MAÏS DE BUKANGA-LONZO CONTAINER STORE IN MUSINA
The first Container Store has been placed in Musina. Here the maize that was planted and harvested on the S.E. Parc Agro site will be sold. This is a great achievement, the product was 100% locally produced in the DRC and we thank everyone that helped to make this possible.
MAIN ENTRANCE PREPARATIONS HAS BEGUN
The first groundworks have begun for the new entrance. We will keep you up to date with the latest development
S.E. DU PARC AGRO MAIN ENTRANCE
Sneak peak of the main entrance that will be built at S.E. du Parc Agro
MAÏZ DE BUKANGA-LONZO CONTAINER STORES IN PROGRESS
You have seen the advertisement, now you get to see a sneak peak of the new Container Stores that will be selling “MAÏZ DE BUKANGA-LONZO”. The first store is almost ready to be revealed. We will be posting this event tomorrow on our website with media links, as well as on the Facebook site.
BEDNAR ATLAS HO8000 ARRIVES AT S.E. PARC AGRO
The first Bednar Atlas HO8000 arrived at the Parc today in 3 containers
SILO PROGRESS
Please follow the silo progress in the gallery under “SILO COMPLEX CONSTRUCTION IS COMING ON NICELY”
NEW CELLULAR TOWER
Vodacom erected a new cellular tower on the S.E. Parc. It went live on the 5th of September 2015
MAIN ENTRANCE PROJECT
Discussion for the Main Entrance has started. We will start with this new and exciting project very soon
CASAVA PROJECT IN FULL STEAM
AIRCRAFT HANGAR COMPLETED
EXCAVATION OF THE RIVER FLIGHT PUMP STATION
Excavation of the river flight pump station begun on the 27th of August at 9h00. Yesterday they reached the required depth of 3,5 meters below the river level. Luckily there was no water filtration and everything went according to plan
SILO COMPLEX CONSTRUCTION IS COMING ON NICELY

NEW TELEVISION ADVERT FOR MAÏZ DE BUKANGA-LONZO
The new television advert for Maïz de Bukanga-Lonzo aired yesterday in the RDC. The maize for this meal was planted and harvested locally at S.E. du Parc Agro. After harvesting it was transported to the milling plant in C.D.I.-Bwamanda Kinshasa, where it was processed and sacked for distribution. We thank each and every one who helped to make this happen. We are all very proud and honoured to be a part of this.
PVC PIPE PRODUCTION STILL GOING STRONG
2 500 meters of PVC Tubing produced for the past week
BUHLER VERSATILE TRACTORS ARRIVE IN MATADI
We are excited to share with you that the Buhler Versatile Tractors that left South Africa a few months back have arrived. Two of the tractors are already loaded and on their way to the “Parc” in Bukanga-Lonzo
MANUFACTURING PVC PIPES LOCALLY
During the past few weeks we have been busy setting up to produce our own PVC pipes. To be able to do it ourselves locally, is a great achievement. We produced 560 meters of pipe with measurements of 50 mm x 5 mm in a mere 24 hour run. Everyone on the “Parc” is very excited and proud of this operation.
OUR NEW FACEBOOK PAGE
We are proud to say that we have entered the social media scene with a new Facebook page. Come browse through our page, like and share with friends and family. Find us “S.E. Parc Agro Industriel de Bukanga-Lonzo”
HOSTEL PROGRESS
The first two hostels are practically finished. Final touches like air conditioning, showers, water and electricity supply will be attended to in the coming weeks. Construction on hostel three and four will commence on Friday. We will keep you up to date.
LOGISTICS
Three of our JAC trucks will transport 60 tons of maize to the mills in Kinshasa. Afterwards they will return with approximately 90 tons of lime to the farm
BRICK PRODUCTION
We produce about 500 bricks per day these are used for construction purposes
NEW WAREHOUSES
Construction of warehouses are progressing fast. Each warehouse is approximately 600 m2 and will be finished by next week
AIRCRAFT HANGAR NEAR COMPLETION
We are excited to say that construction is near completion. Only cladding on one side remains and instillation of the hangar doors

THE FIRST GREEN PEPPERS PICKED
The first green peppers were picked from the local vegetable garden on the site. This gives hope to those in the area for fresh, locally grown products. For most of them these are the first vegetables they have ever eaten
NEW GRAIN STORAGE FACILITY READY FOR CONCRETE WORKS
Construction is moving along swiftly with the first silo ready for concrete work. We willkeep you updated with the progress, in the meantime you can view images in the Gallery section under Construction of the Grain Storage Facility.
BUCKET ELEVATOR PIT AND CONVEYOR TRENCH AT THE SILO SITE
CONSTRUCTION CONTINUES SWIFTLY FOR THE OTHER HOUSING STRUCTURES
FIRST HOUSING STRUCTURES COMPLETED
CONSTRUCTION OF MEDICAL CLINIC UNDERWAY
CONSTRUCTION OF COMMUNITY CENTRE WELL IN PROGRESS
MECHANICAL WORKSHOP FINISHED
Here all the repairs and maintenance will be done on mechanical equipment. Practical training will also be held here in various mechanical areas to better equipped the workers with the right skills for the trade
PREPARATIONS FOR SECOND WATER RESERVOIR
FIRST WATER RESERVOIR FINISHED AND FILLED WITH WATER
This reservoir will be used with others to supply water for building and farming purposes
CONSTRUCTION ON S.E. PARC AGRO BOOMING
The past few weeks’ construction on S.E. Parc Agro has been booming. So much progress has been made, from the construction of several Housing Structures, a Medical Clinic, Mechanical Workshop and even a new Airplane Hangar.
AIRPLANE HANGAR CONSTRUCTION
S.E. PARC AGRO DEVELOPMENT NEWS
Yet another function has been added to the already extensive S.E. Parc Agro Development in the form of a milling plant in C.D.I.-Bwamanda Kinshasa. Harvested maize crops from S.E. Parc Agro are processed into maize meal and packaged to be sold to the local population.
GROUND PREPARATION BY APPLYING TRIOMF LIQUID LIME TO THE GROUND
Currently on the park we are busy drying maize that's been harvested the past few weeks
A NEW COMBINE TABLE HAS ARRIVED
This table is specifically used for soy and dry beans

THE ELECTRICAL SUBSTATION AT S.E. PARC AGRO IS TAKING FORM
OFFICIAL GROUND BREAKING DAY
The 7th of May 2015 marked the official Ground Breaking Day at the site of the Marché International de Kinshasa. Fresh produce such as vegetables, grains, meat and fruit, will in future, be supplied here from S.E. Parc Agro Industriel de Bukanga-Lonzo daily to Marché International de Kinshasa. The new Marché International de Kinshasa will house large volumes of fresh products creating a platform for fresh produce trading. High-level commercial food trading principles at a domestic and international level will be active within Market incorporating E-commerce through a complex web-based trading system. Price regulations and benchmarks will control both the local and export markets. Daily auctions will be held. This market concept will create a very affordable basis for locally produced food products. For more about Marché International de Kinshasa please follow the link click on the following link kinfrais.com
MAIZE DRYING AND STORAGE
Currently on the park we are busy drying maize that’s been harvested the past few weeks. Maize go through this process if the moisture percentage is too high for storage. After the drying process the maize is stored in silo bags
Coming soon
PUMP STATION AND DAMS
An intricate and state-of-the-art water supply scheme has been developed to make advanced irrigation on the farm possible. Water from the river is stored into a riverside reservoir for further distribution to the central pivot irrigation system. Two 630 mm steel pipes will convey water from the reservoir with super-powered pump installations to the plateau, 280 m upwards into a secondary reservoir. Pump booster stations will take the water 3.2 km further to two large lined dams from where it will supply the central pivots.
VEGETABLES
Carefully selected vegetable cultivars suited for economic food supply will be planted on the 1 000 ha of irrigated land. The vegetable agricultural unit will employ at least 5 000 labourers to cultivate the area by planting, weeding, and harvesting all-year produce. Specialized plant food will be applied to maximize growth and nutrient content of vegetables. Once harvested, vegetables will be stored in warehouses from where it will be cleaned, processed and distributed as fresh produce.
TRAINING CENTRE
A fully-equipped Training Centre will be erected towards the end of 2014 as the hub of labour-related education. Skills-related training will be a major and on-going focus at the S.E. Parc Agro Training Centre with professional tutors using the best in technology and teaching techniques. Machine-specific education will form part of this general agricultural information centre, ensuring up-to-date knowledge of every aspect of farming and land cultivation.

COMMUNITY FACILITIES
To complete the housing development at S.E. Parc Agro de Bukanga-Lonzo, well-planned and placed facilities will be built to ensure a balanced social lifestyle for residents. The church will provide the necessary gathering point to worship and engage in fellowship. Sport facilities such as a soccer field will further enhance recreational activity of the residential area.
SOCIAL DEVELOPMENT
To aid and equip local village farmers in small-scale agriculture, the WALK BEHIND TRACTOR cultivator is available to at least 1 500 local farmers. This implement is easy to operate, effective and long-lasting in harsh African conditions. It is furthermore highly cost-effective in terms of fuel consumption and labour input costs. Development of agriculture production at micro-level is of importance to sustainable food production and food security.
CHICKEN PROJECTS
An advanced chicken production unit will be established on the farm for the production of various products. 50 000 baby chicks will be flown into the farm daily and kept in hi-tech chicken growing pens. A hatching unit is planned to be active within 12 months after the large-scale marketing of the first grill-chickens. Between 45 000 – 50 000 chickens will be transferred daily from the chicken growing pens to the on-site abattoir for processing and packing. Finished chicken meat products will be moved to the cold storage facility from where it will be distributed through the cold-chain transport system to Marché International and other wholesalers.
ABATTOIR
A fully-equipped highly functional abattoir will form part of the chicken production unit. This abattoir will comply with international health standards. Slaughtering and processing of fresh chicken meat will occur daily to make speciality cuts and packaging possible. As an integral part of the fresh meat supply-chain, the abattoir will utilise skilled labour and precision equipment to ensure quality output.
COLD STORAGE
Freshly harvested and processed vegetables together with freshly packed chicken meat will be stored and managed in a cold storage facility on the farm. These advanced and automated product preserving storerooms form the foundation of the food cold-chain system. Various temperatures according to specific product and lifespan requirements can be accommodated and applied throughout the entire cold storage facility from where distribution can take place.
PACKAGING
The custom packaging of processed vegetables and chicken will take place on the farm by trained packers. A variety of package options of special meat-cuts and ready-to-use vegetables will become available and distributed from the cold storage facility to various markets. This process is vital in the fresh produce supply-chain of locally grown food products and the import and export thereof. Effective packing principles preserve fresh produce naturally to ensure maximum shelf-life.

DISTRIBUTION
Once fresh produce including cultivated vegetables and packed chicken is ready to be taken to the marketplace, products will be transported from the cold storage facility to the off-set points in and around Kinshasa. Logistics will include the use of 50 sophisticated 10 ton cool trucks to convey freshly preserved produce to markets such as the Marchè International and other destinations. Distribution of products will be daily and ongoing, 365 days of the year.
ORCHARDS
NitreX™ will be applied as a top dressing with a TRIOMF foliar feed later to enhance perfect fruit production within this initial fruit orchard.
SCHOOL
The building of a multi-level school incorporating pre-school, primary and secondary school facilities, to be completed by June 2015.
Gallery
Images
GREENHOUSE STRUCTURE CONSTRUCTION
WEIGHBRIDGE CONSTRUCTION
CASSAVA FACTORY CONSTRUCTION
TURNING ON POWER CEREMONY
AFRICAN DEVELOPMENT BANK GROUP VISITS S.E. DU PARC AGRO
NEW EQUIPMENT ARRIVE FOR QUARRY WORK
MAÏZ DE BUKANGA-LONZO CONTAINER STORES
POWER STATION
PREMATURE VISITS S.E. PARC AGRO
RIVER FLIGHT PUMP STATION
MINISTER OF AGRICULTURE PAYS A VISIT TO S.E. PARC AGRO
MAIZE PROGRESS 2015 SEASON
BUHLER VERSATILE TRACTORS AND NEW BEDNAR EQUIPMENT READY TO START WORKING
POWERLINE
PIVOT DAM
WATER AND ELECTRICITY TRENCH
S.E. DU PARC AGRO MAIN ENTRANCE
MAÏZ DE BUKANGA-LONZO CONTAINER STORES
BEDNAR ATLAS HO8000 ARRIVES AT S.E. PARC AGRO
NEW CELLULAR TOWER
MAIN ENTRANCE PROJECT
CASAVA PROJECT
EXCAVATION OF THE RIVER FLIGHT PUMP STATION
SILO COMPLEX CONSTRUCTION
MANUFACTURING PVC PIPES LOCALLY
GROUD PREPARATION
LAND SURVEYING
LOGISTIC SERVICES
AIRCRAFT HANGAR
VEGETABLE GARDEN
WATER RESERVOIRS
STONE CRUSHING PLANT
ERECTION OF FIRST PIVOTS’
TEMPORARY BRIDGE
HARVEST DAY @ BUKANGA-LONZO | 5 MARCH 2015
LIFE IN AND AROUND BUKANGA-LONZO
AGRONOMISTS
ARRIVAL OF FIRST EQUIPMENT
CLEARING VEGETATION
TEMPORARY LIVING QUARTERS
ROADWORKS
ARRIVAL OF PLANTERS
ARRIVAL OF AIR TRACTORS
S.E. PARC AGRO INDUSTRIEL DE BUKANGA-LONZO LAUNCH
LOGISTICS BUILDINGS
MEDICAL CLINIC
FIRST BATCH OF FERTILIZER ARRIVES ON FARM
PLANTING 1 200 HA
CONSTRUCTION OF FUEL POINT
APPLIED FERTILIZER BY AIR TRACTOR
HARVESTERS ARRIVE
HOUSING STRUCTURES
GROWTH PROGRESS OF THE FIRST 5 000 HA
NEW EQUIPMENT ARRIVE AT S.E. PARC AGRO
MIXING AND MANUFACTURING OF FERTILIZER
DELEGATES FROM DIFFERENT INSTITUTIONS VISIT S.E. PARC AGRO
CONSTRUCTION OF THE GRAIN STORAGE FACILITY
BUHLER VERSATILE TRACTORS
Contact Us
PARC AGRO is part of the
Africom Commodities Group of Companies
PARC AGRO Copyright © 2015. All rights reserved.
Privacy Policy | Disclaimer
Designed by MPower Media
Contact Us:
Appt 1 & 2 Immeuble FIKHUSS,
65 Boulevard Tshatshi, Gombe Kinshasa,
Democratic Republic of Congo
Tel: +243 854633574
Fax: +27 86 541 7948
Email: info@parcagro.com